Notification Window

Procedures at a Glance

from permits to warranty reviews

Select MORE >> within each topic to see the full article 

2

1.0 Before Construction Begins

overview

It is very important to review the Construction Contract before construction begins because it outlines the responsibilities (and therefore possibilities for liability) of the consultant in administering and managing the construction phase of the project. More >>
2

1.1 Reviewing the Contracts

chop + ccac commentary

The construction contract administrator needs to get well organized prior to construction start up. One of the first steps should be reviewing the contracts.  More >>
2

1.2 Regulatory Requirements

CHOP + CCAC COMMENTARY

Construction of sound, safe buildings and structures is fundamental. Building codes and regulations provide these minimum safety standards...More >> 
2

1.3 Assembling the Construction Documents Sets

CHOP + CCAC COMMENTARY

The construction contract administrator should review the permit documents after the building permit has been issued and ensure that any notations... More >>
2

1.4 Holding the Project Kick-Off Meeting

CHOP + CCAC COMMENTARY

Once the Owner selects a Contractor, a pre-construction meeting shall be called to introduce the parties involved in the construction phase...More >>
2

2.0 During Construction

chop + ccac comments

The standard stipulated-sum construction contract,  and the client-architect afgreement require the architect to perform a number of duties and/or tasks. This can include: review shop drawins, samples, product data submissions, and prpvide timely interpretation of the contract by...
More >>
2

2.1 Attending/Conducting Progress Meetings

chop + ccac comments

The tone, format, and efficiency of all subsequent meetings is often set at the pre-construction meeting. The architect should be well prepared for this first meeting.-construction meeting. More >>
2

2.2 Construction Reviews

chop + ccac comments

The architect should establish credibility on the job site from the start of the project. This is accomplished through a detailed knowledge and understanding of the project and the contract documents. More >>
2

2.3 Responding to Requests for Information

CHOP + CCAC COMMENTS

A Request for Information (RFI) is useful throughout the design and construction of a building project as a tool for the owner, architect, contractor or other party to request... More >>
2

2.4 Reviewing Submittals

chop + CCAC COMMENTS

Shop drawings ensure and confirm the accuracy, size, and other specific data about a product or material prior to final purchase, fabrication or delivery. More >>
2

2.5 Review by Third Party Consultants and Inspectors

chop + CCAC COMMENTS

Independent inspection provided by specialist inspection and testing firms is required on most construction projects. More >>
2

2.6 Reviewing Substitutions and Alternates

excerpt from aia + CCAC COMMENTS

Product substitutions are a normal part of construction; few projects get built without at least one substitution request being submitted (if not approved) More >>
2

2.7 Changes in the Work

CHOP

Change Orders cover adjustments to the scope of work that require a change changes to the Contract Price or Contract Time. Sometimes the process for making changes can be demanding and time-consuming.      More >>
2

2.8 Certifying Payment

chop + CCAC COMMENTS

In typical stipulated-sum construction contracts, the architect is responsible for preparing Certificates for Payment indicating when and how much a client must pay the contractor. More >>
2

3.0 As Construction Ends

CHOP 

As the construction of a project nears completion, there are a variety of tasks that must be completed to ensure that the building conforms to the design contract.    
More >> 
2

3.1 Certifying Substantial Performance

CHOP + CCAC COMMENTARY

The first step in the take-over process is certification of substantial performance of the work. Under the terms and conditions of... More >>
2

3.2 Managing Requests for Occupancy 

CHOP + CCAC COMMENTARY

Unconditional Occupancy occurs when the scope of work associated with a building permit and building code compliance is complete and accepted... More >>
2

3.3 Conducting Deficiency Reviews

CCAC COMMENTARY

Before Substantial Completion or any occupancy takes place an initial review and list of deficiencies is prepared by the contractor per OAA/OGCA Document 100...
More >>
2

3.4 Project Closeout Procedures

chop + ccac commentary

Take-over procedures are a normal part of the architect’s basic services performed at the end of contract administration. After take-over, the architect is responsible for... More >>
2

3.5 Completion

CHOP + CCAC COMMENTARY

Prior to occupancy of the building by the owner, the contractor forwards various items and documentation to the architect for review. These may include… More >> 
 
2

4.0 After Construction Has Ended

CHOP 
As the construction of a project nears completion or after the building is complete, the architect continues to provide professional services to the client. Some of these services… More >>
2

4.1 Preparing & Issuing Record Drawings

CHOP + CCAC COMMENTARY                        

It is important that the architect not represent that the record drawings are claiming to be the way that the building was in fact constructed. The following sample...More >>
2

4.2 Commissioning

CHOP + CCAC COMMENTARY        

Commissioning includes a range of activities undertaken to transform the design of a facility into a fully integrated and operating system. It is a process of quality assurance which... More >>
2

4.3 Arranging & Conducting Warranty Reviews

CHOP + CCAC COMMENTARY                        
The architect will be responsible for reviewing  defects and deficiencies during the warranty period on behalf of the client... More >>