1.4 Issuing the Bid Package

The issuance of the bid package is discussed in CHOP v3, Chapter 6.5, “Distribution of Bid Documents” and identifies steps taken for the traditional method of construction procurement, with reference to electronic tendering services.

The process is similar whether using the traditional method or electronic method of construction procurement and as has already been noted, the biggest difference being the number of printed documents that the owner is required to provide. The steps are similar in that they both include;

  • Issuing a notice of bid to potential bidders, this notice should identify things such as ;

    o the bid calling authority and contact information
    o the method by which a bidder is to register as a bidder
    o how the bid documents are to be obtained
    o the deadline and location for submission of the bids
    o the date, place or method for a mandatory bidders conference or site visit

    If a traditional method of construction procurement is being used, some additional steps may include;

  • Printing of bid documents for distribution
  • Identifying whether there is a bid document deposit
 
 
Share
Contracts banner

OAA Contract Suite

Did you know the OAA offers free contracts for its members and the general public? These downloadable standardized contracts make it easier for all to enter into fair, balanced business relationships.

MORE
BlOAAg logo

BLOAAG - Design Excellence Finalists

Check out our 2024 Design Excellence Finalists! This year's collection features a diverse range of building types.

MORE
Events banner

Events Calendar

Check out our events calendar for a wide array of online and in-person events. Also submit an event using our new online form.

MORE